:: Projects
Al-Duqum IWPP
Background
Oman Power and Water
Procurement Company (“PWP”) has identified a need for new
procurement of a new Water and Power Plant in the Sultanate of Oman.
This procurement shall be by the way of a fair and transparent
competition for a new Independent Water and Power Project (IWPP).
The IWPP will be Coal fired and will be located in the Duqm area
close to Duqm Port with expected power capacity of about 1000MW
Project Time Schedule
|
Appointment of Advisors |
October 2009 |
|
Issue of Request for Qualification (RfQ) |
May 2010 |
|
Issue of Request For Proposal (RfP) |
October 2010 |
|
Award of IWPP |
August 2011 |
|
Early Power Date |
1st April 2015 |
|
Commercial Operation Date |
1st April 2016 |
Project Status
Financial and Technical Advisory Services have been awarded to KPMG
and Worley Parsons respectively. Legal Advisory Services were
awarded in November 2009. The Project Advisory Services are
progressing on schedule.